If the fill is determined to be 6,160 LCY and the cut is 5,280 LCY, how much more fill is required?

Prepare for the NASCLA Accredited Exam with flashcards and multiple choice questions, each featuring hints and explanations. Excel in your exam!

To determine how much more fill is required, you need to compare the amount of fill needed to the amount of cut that has been established. The fill required is given as 6,160 LCY, while the cut is 5,280 LCY.

To find out how much fill is still needed, subtract the amount of cut from the fill amount:

6,160 LCY (fill) - 5,280 LCY (cut) = 880 LCY.

Thus, 880 LCY of additional fill is required to meet the project's needs. This calculation emphasizes the importance of understanding earthwork quantities, where fill and cut volumes must be carefully considered to ensure proper grading and site preparation.